Home » News » Local News » Nevada Street Phase 2 Ready to Award!
By Jerry Henry on August 14, 2018.
The Nevada Street Sidewalk, bike lane and road improvement project is back on again. Auburn City Council will consider bids at tonighta s council meeting. Gabe Mendez Inc. on Newcastle – the contractor on the first phase of the project – came in with the low bid of $4.34 million. McCuen Construction Inc. of Loomis’ bid was $4.42 million.
With a 10 percent contingency added to the Mendez bid, Auburn staff is recommending that the City Council award the project to the low bidder, allocating a total of $4.78 million. The project will cover a section of Nevada Street that does not now have a sidewalk which stretches from Fulweller Avenue to the inter-state on ramp to I-80.